EWB UK Placement - Philippines

Monday, December 18, 2006

Project Management

The flow chart desribes the process followed for the installation of a community based wind energy system. 4 months into the project the pre-feasibility studies have been completed and the project is into the system design and full feasibility study. Fabrication of three wind turbines is also ongoing.




0 Comments: